Al Gurg Building Services


2022

Dubai

Solar

Al Gurg Building Services was looking for a solution that could reduce utility energy consumption and minimize operation cost. TTE’s Solar team were commissioned to propose a rooftop solar plant for this purpose. The scope of work included installation of 912kWp on the factory roof, a solar system designed to factor in the 65% energy requirements of the factory, with the rest fulfilled from the DEWA Grid. The challenge posed for the team while working on this project was that the factory was built in 1962 and hence the integration of the solar system with DEWA Grid was difficult. Nonetheless, the team managed to find a viable solution and complete the project successfully.

See similar projects


ECIG Head Office

Scientechnic Warehouse

Mercedes Benz Showroom

View all

You may also be interested in